Project: Stubbo Solar

Stubbo Solar

Client: ACEN Australia

Value:

Completed: 2024

Project Description:

The project required extensive efforts, including 38 kilometres of MV trenching and excavation, 5 kilometres of fibre/earthing/LV trench, and 49 kilometres of DC trenching and excavation. Additionally, we installed 240 kilometres of MV cable, 350 kilometres of fibre/earthing/LV cable, 301 kilometres of DC cable, and 315 kilometres of underground string cable.

Completing these deliverables was a significant achievement. Over 50 dedicated JLE team members, supported by more than 30 pieces of equipment, worked tirelessly throughout the project. Despite the challenges, our strong collaboration with PCL Constructions and ACEN Australia ensured the project was completed on time and within budget. The JLE team takes great pride in these accomplishments and looks forward to expanding our capabilities in the renewable energy sector.